Generator Factory and Site Acceptance Testing FAT and SAT

A generator that runs for a minute with no load on handover day has not been tested. The factory test proves the set gives its rated output before it ships, and the site test proves it works with your panels and real loads. This is what each test should cover and what you receive with it.

Wiring the transfer panel before testing
9 to 3,500kVA new diesel generators
24 monthswarranty on new sets
6 brandsauthorized dealer for every brand we sell

The two tests side by side

ItemFactory test FATSite test SAT
WhereAt the assembly plant before shippingOn your site after installation and wiring
What it provesThat engine, alternator and controller give the rated output, voltage and frequencyThat the set works with the transfer panel, cables and the real building load
Load usedA load bank in steps up to full loadA load bank or the building load, as the spec says
What you receiveFactory report with readings and engine and alternator serial numbersTest report with readings and the commissioning checklist

What happens in the factory test

Load in steps

Runs at 25, 50, 75 and 100 percent of rating, logging voltage, frequency, current, engine temperature and oil pressure at each step.

Sudden load

A large block of load is added at once and then removed, measuring the voltage and frequency dip and recovery time. This is what happens when a pump starts or the whole building transfers.

Protection devices

Shutdown on high engine temperature, low oil pressure and overspeed is tested, along with the emergency stop.

Serial numbers

Engine and alternator serial numbers are checked against the quote and the certificate of origin, so you receive the model you agreed on.

What happens in the site test

Checks before first start

Mounting, oil and coolant level, battery, earthing and phase sequence before the first run.

Transfer panel ATS

Mains is actually cut and the time for the building to move to the generator is measured, then mains returns, the load transfers back and the set cools down before it stops.

Load run

A run on real load or a load bank for the time set in the spec, with readings logged at fixed intervals.

Sets in parallel

Where there is more than one set, load sharing is tested, and one set leaves and rejoins without the building losing power.

Training and handover

The operating team is trained to start, stop and read alarms, and receives the manuals and the test report.

What to write in your enquiry so nobody argues about it later

  • Whether you need a factory test witnessed by your engineer or consultant, or the factory report is enough.
  • Load steps and the duration of each step in the site test.
  • Who provides the load bank and the diesel during testing.
  • The report template, if your organisation has its own.
  • Any standard the project requires, such as ISO 8528 for generator performance or NFPA 110 for healthcare facilities.

At handover and commissioning we run the set on load and hand over a report with the readings, and the quote states what each test covers and what it needs from your site.

Common questions

Does every generator need a factory test?

Hospitals, data centres, government projects and large sets usually have it in the spec. For smaller sets the factory report plus a site test is usually enough.

Why is a no load run not enough?

A no load run does not show a weak engine, alternator or regulator. Long running with no load also harms the engine, because the diesel does not burn fully and builds up in the exhaust.

What is the difference between a load bank and the building load?

A load bank is a resistor unit that loads the set at a fixed, known level, so the readings are precise. The building load proves the set works with your real loads, but it rarely reaches full rating.

Are the generators new?

Yes, new sets only, with a 24 month warranty.

Need something else?

Need a generator with set tests?

Send the size, the project spec and the tests you need, and we will send a written quote stating what each test covers.