Sizing is the most important decision in any generator project. An undersized unit trips or gets damaged when heavy loads start; an oversized one costs more to buy or rent and to fuel, and running it lightly loaded for long periods harms the engine itself.
This guide follows the method our engineers use in a load study, in steps you can start on yourself before asking for a quote.
kW versus kVA
Equipment is usually rated in watts or kilowatts, while generators are sold in kVA. The difference is the power factor, which for most diesel generators is 0.8.
| Conversion | Formula | Example |
|---|---|---|
| kVA to kW | kVA × 0.8 | 100 kVA ≈ 80 kW |
| kW to kVA | kW ÷ 0.8 | 60 kW load ≈ 75 kVA |
Step 1: list every load
Write down every device the generator will run and its rating, from its nameplate or catalogue. Split them into two groups:
- Steady loads: lighting, computers, screens, heaters. They draw roughly the same power all the time.
- Motor loads: air conditioners, pumps, compressors, lifts, workshop machines. These draw several times their running current when they start, even if only for seconds.
Typical values for illustration only; the exact figure is on each device:
| Device | Approximate running power |
|---|---|
| 1.5-ton split AC | 1.5 – 2 kW |
| Household fridge | 0.15 – 0.3 kW |
| LED lighting, mid-size office | 0.5 – 1 kW |
| 2 hp water pump | about 1.5 kW |
| Small welding machine | 4 – 6 kW |
Step 2: allow for motor starting
The most common sizing mistake is simply adding up ratings. A motor needs far more power for a moment when it starts, so if several ACs or pumps start together the voltage can dip and the generator can trip.
- Start large loads one after another, not all at once.
- Use soft starters or variable-speed drives on large motors.
- Choose a size that can start the largest motor while the other loads are running.
Step 3: add a safety margin
After totalling the loads and starting currents, add a margin of around 20 to 25 percent. It keeps the generator from running flat out all the time, covers loads added later, and offsets the output loss in high heat or at high altitude.
Worked example: a small workshop
Four air conditioners (2 kW each), 1 kW of lighting, a 5 kW welder and a 3 kW air compressor:
- Total load: 8 + 1 + 5 + 3 = 17 kW.
- Allow for compressor and AC starting current, rounding up to about 24 kW.
- Convert: 24 ÷ 0.8 = 30 kVA.
- With a 20 percent margin: about 36 kVA, so a 40 or 45 kVA generator fits best.
This is an illustration; in practice we study the actual loads on site before recommending a size.
When do you need more than one generator?
For large or critical facilities such as hospitals and factories, two or more synchronised generators are often better than one very large unit: part of the capacity keeps running if one unit is down for service, and the number of running units can follow the load.
We delivered this approach at hospitals (two generators, 1,565 kVA in total) and at giga-projects (nine 1,000 kVA generators). See our synchronising and transfer panels.
FAQ
Should I just pick a much bigger generator?
No. A much larger unit costs more to buy and fuel, and long periods of very light load harm the engine. A 20 to 25 percent margin is usually right.
Where do I find my equipment ratings?
On the device nameplate, in the manufacturer catalogue, or from your electricity bill for average consumption.
Can you do the load study for me?
Yes. Our engineers visit the site or review your equipment list, then recommend the size with a quote.
Your next step
Let’s size it together
Send your equipment list or a photo of your electrical board and we’ll reply with a recommended size.